Telecom for New Builds: The Sooner, the Better
Published on 02/12/2025 in Service
Proximus is in the middle of a true fiber marathon. By early 2025, 2.3 million homes and businesses already had access. Your buyers and tenants can also benefit from ultra-fast internet from day one. The key condition? You must register your new construction project with Proximus immediately after the building permit is approved.
A golden rule for homebuilders: “Got the building permit? Then it’s time to start with telecom.” That early? Yes—just like with water and electricity, you should request the Proximus network connection before the first shovel hits the ground. Discover how this saves you time, money, and earns your client’s eternal gratitude — and how to register your project.
Register your project with Proximus here Opens a new window
Registering Your Project for a Proximus Network Connection
Are you starting a new construction project? Or contributing to one? Proximus prefers to connect the building to the new fiber infrastructure. That’s why it’s important to request the connection as early as possible — right after the building permit is approved. In areas without fiber, several steps are needed to make it available. You can request the connection via the “ New Connection Request ” form.
Online from Day One
Requesting the telecom connection on time has three major benefits:
- Fiber or copper: You’ll know early on which technology will be used. Proximus provides your electrician with technical sheets for the preparatory work.
- Your clients are guaranteed connectivity - internet, phone, and TV - from the moment they move in. A must-have for many, and a dealbreaker if it’s not ready.
- Where possible, we coordinate with other utility companies to align the work. That way, we only need to dig once.
Connection in 3 Steps
Step 1: Notification
Requesting a Proximus connection sets several actions in motion:
- The Proximus construction team conducts a technical study to determine the technology (fiber or copper).
- They contact other utility companies to coordinate the timing of the works. This way, one excavation can prepare for water, electricity, and Proximus services.
Step 2: Permits and Preparations
While Proximus arranges all necessary permits for public domain work, you prepare the site. For example, your electrician must install waiting ducts, cable trays, and a telecom panel. In apartment buildings, cables must also be installed from the technical room to each floor. All steps are detailed in the technical guidelines.
Step 3: Connection
During the works, Proximus will contact you occasionally. Are the preparations complete? Is the timeline still accurate? If so, they’ll proceed with the final connection.
Massive Fiber Rollout
We’re sending and storing more and more data online. That’s why the fiber rollout is so important — it enables the transfer of massive amounts of data at lightning speed, without disruptions or delays. By early 2025, 2.3 million homes and businesses had access to fiber. And every 13 seconds, a new connection is added. Requesting a new connection? Check which technology your project will be connected to.
You Spark It, Proximus Fuels It
“You can’t have a fire without a spark,” Bruce Springsteen already knew in the ’80s. If you provide the spark — by submitting the request right after the permit — Proximus brings the fire: ultra-fast internet from the moment your client moves in.
Learn everything about (re)building and telecom connections at www.proximus.be/construire .