Building or renovating?

Planning for your connection

to the Proximus infrastructure

It's important to foresee your connection to the Proximus infrastructure during the construction/renovation phase. That way you avoid more digging work later. Nobody likes the front yard to be distroyed, for cabling… You’re free to choose Proximus later on, for your products and services.

Request your connection when the structural works are done and roof, windows and doors are placed. The connection will coincide with other providers (water, gas, electricity and sewage system).

Request your connection

Preparatory work for the connection

  • Dig a 60-cm-deep trench, in a straight line and perpendicular to the building line
  • Install a hard, smooth-walled PVC conduit for future cables. The conduit should be 50 mm in diameter with a cable pull-wire that exceeds by 50 cm at each side.
  • The conduit should enter the construction via the energy curve or via an opening in the masonry.
  • Both sides of the conduit should be hermetically closed by a par un removable plug
  • Donc forget to foresee a picket to localise the far end of the conduit at the side of the street.
Trips and tricks for this phase
  • When your electrician comes by to do the electrical works, ask him to install the "Smarttube" as well. This is a cable certified by Proximus. Your electrician can take care of everything; you don't need to be present during the installation.
  • Require more info about the instalation of a future proof network in your home? Check our advice here. (.pdf)

Request your connection

Some extra tools for you!

The move checklist

You’ve got a lot on your mind, help is here. A cure to your stress: our move checklist helps you plan it all!

Less stress, to the checklist

Which moving type are you?

Take a break and do the test.
Sit down, answer the questions and discover your moving type!

Let’s do this test!
Contact us